VolNET Quarterly Reports |
---|
January 2001
Tennessee.edu Domain
Completion of dual email addresses for all campuses is nearing the final stages. There are approximately 25 remaining faculty and staff with naming conflicts that will need to choose their new name by January 30.
All machines that can currently be moved from the UTENN domain have been moved. Aliases have been set up for machines that were unable to change their names and appropriate changes have been made to local host config files (/etc/hosts.equiv and lmhosts files).
The consolidation of the Administrative Services Groupwise post offices into one central post office was successfully completed in November.
Core Network & Electronics
Orders for core electronics for January & February buildings have been placed, however, Cisco has been experiencing shipping delays on the orders. Plans are to order March and April equipment as soon as possible to avoid shipping delays.
The new DNS/DHCP servers that will handle the assignment of IP addresses on the Knoxville campus continue to be configured with the NetId product. Initial building cutover problems have occurred and the software is being evaluated to determine if it is feasible to continue using it.
All buildings on campus have been reviewed and prioritized and the proposed cutover dates have been posted to the Volnet website. Plans are to meet with building representatives for each months list of buildings as early as three months prior to cutover. November, December, and January building representatives met on October 5 & 6. February and March building representatives met on December 7 & 8. In addition, there were individual departmental meetings held with November, December and January representatives. The original schedule was delayed one month with Burchfiel being cutover on December 15, at their request. Likewise, Claxton was rescheduled for January 5 at Computer Sciences request. Due to the occupancy of three dorms, only nine of the twelve dorms were cutover by December 31, with the remaining three dorms scheduled for the first week in January. University Housings ports in these areas were not cutover in order to allow them to upgrade their Novell server and applications. Those ports will be cutover in November 2001. Over 1500 desktop machines were visited and configured by Pomeroy employees and LaDS in anticipation of building cutovers.
Current IP issues have been documented with a white paper that has been published to the Volnet website.
IP-only routing tests will be performed in all buildings prior to building cutovers.
Fiber Build-Out
In October fiber was installed from the vault to Burchfiel and Claxton. Ayres, Claxton Addition, Hoskins and South College were connected to the vault in November. In December fiber was installed from the vault to Apartment Residence Hall, North & South Carrick, Clement, Gibbs, Greve, Hess, Humes, Massey, Melrose, Morrill, Reese, Strong, Thornton and Jesse Harris.
Intra-Building Wiring
SMC To be finished by the end of February Student Services Admissions and Records has been rewired Physics On hold by order of Fire Marshall Nursing On hold by order of Fire Marshall Hodges Library To be finished by the end of May Vet Med Site survey currently underway Jesse Harris To be started July 1, 2001 In addition, discussions with appropriate personnel have occurred to determine if Andy Holt Tower should be moved up in the wiring timetable to address potential SAP/IRIS implementation problems for April. At this time Administrative Services has declined to move AHT ahead in the wiring timetable; however, there will be a network stress test performed on Wednesday, January 29 to identify network performance issues concerning IRIS.
Internet
A DS-3 line from QWEST will be installed January 15-30 to address saturation problems with our commodity internet. The TNII circuit has been cancelled.
Staffing
Network Services interviewed candidates and submitted a request for approval to Dr. McCay in late December for the three open positions.
An LDA position was created and filled in December to address IP numbering.
Wireless Networking
Site surveys have begun and have been completed for four buildings. Plans are to develop and document an installation plan within the next quarter. |
Question? email the webmaster. Division of Information Infrastructure |